Signage replacement across 14 industrial buildings
JTC
Summary
Signage replacement programme delivered 3 weeks ahead of schedule.
Problem
Boom lifts could not reach overhead signage anchors.
Approach
Rope access with parallel four-rope setup and night shift.
Outcome
Programme completed ahead of regulatory deadline.
Metrics
14 buildings · 3 weeks early · 0 incidents